Issues Accompanying Dam Removal

PrintPrint

Issues Accompanying Dam Removal

One of the issues accompanying dam removal is the potential impact of the large volume of sediment that accumulated behind some dams over time. This so-called "legacy sediment" is commonly very fine-grained and contains stored nutrients and organic matter, among other possible pollutants. When dams are destroyed, efforts must be made to avoid a large flux of this sediment downstream as the newly released river cuts down to its natural base level. This requires careful engineering and significant funding. Merritts and Walter (2010) have suggested that most rivers and streams in eastern Pennsylvania and Maryland run through floodplains and levees of legacy sediment, not natural river valleys, created by the plethora of small dams built to impound water for hydropower in the past. And, even now, some large dams serve as a buffer against sediment transport that would create broad mudflats and high turbidity in coastal bays such as the Chesapeake Bay. Conowingo Dam in Maryland is one such structure that has reached its sediment capacity. During high flow events, sediments carrying nitrogen, phosphorus, and other pollutants enter the Chesapeake Bay. As of 2021, Maryland is working to implement a multi-million dollar strategy to reduce pollutants from entering the reservoir and reduce their flow downstream. For an example of the engineering and costs of removing a dam, check out the San Clemente Dam Removal & Carmel River Reroute Project in central California.

Map of removed dams showed in a previous lesson. Most dams on East coast with others concentrated on other large waterfronts
Figure 13. Map of the lower 48 states showing locations of dams removed from 1936 to 2013. At American Rivers, the locations are clickable to show information on each dam removed.
Source: AmericanRivers.org Used with permission. All rights reserved.
Eastern Portion of U.S Map blown up. Most removed dams along great lakes, and above west Virginia along the coat
Figure 14. Blow up of northeastern U.S. portion of the dam removal map.
Source: AmericanRivers.org Used with permission. All rights reserved.

Many dam removal projects are proposed, but await funding from federal sources—Congress must appropriate funds. Projects on the Snake River and the Klamath River in the west remain controversial, but at least in the case of the Klamath, the removal of four large dams has begun and it’s estimates that this will have lasting benefits on the river, community, and salmon populations. Figure 9 illustrates the consequences of waiting for funding of dam removal using the Olmstead Dam example.

Graph of Olmsted dam spending, See Caption for description
Figure 15. The costs of waiting to remove and replace dams once approved using the Olmstead Dam and Locks system on the Ohio River. Lambrecht, Bill (16 September 2013). "Costly Dam, Illinois dam costing billions more than expected as delays mount". St. Louis Post-Dispatch. Retrieved 9 March 2014.
Click Here for Text Alternative of Olmsted dam spending graph

In 1988, Congress authorized spending 775 million dollars for a 7-year project to build Olmsted Locks and Dam. But the cost has more than quadrupled to 3.1 billion dollars, and 25 years later, the project is barely half done.

 
Year Funds in millions
1991 5
1993 60
1995 35
1997 70
1999 55
2001 60
2003 70
2005 75
2007 115
2009 115 + 5 in stimulus funds
2011 140
2013 145
2014 163
Source: Army Corp of Engineers